Monday, March 14, 2011

Brickwork and Top Roof Complete

Brickwork and Top roof are complete. Finally we have some protection from the rain! The brickwork took about 3 weeks and the roof 2 days. We are really happy with our roof tile and gutter colour selection. The next job is the render, eaves, external painting and bottom roof. Scaffolding stays up for the render, paint and eaves, then comes down for the bottom roof to be installed. Then work can begin on the internals...






2 comments:

  1. Hi GForce. It's all looking great. Our bricks are so close to being completed, then they ran out. We have received the delivery of the bricks but no bricklayers. Typical isn't it! Hubbie spoke with Barry T yesterday so lets see what comes of that. *rolls eyes* I hope everything will move quicker for you guys now. Bel

    ReplyDelete
  2. Hi GForce, it's been a while since you last posted a photo. How's the building going so far? Can you check my PM from homeone forum?